The Trinity School Board voted to approve a revised maximum project cost and a new maximum building construction cost for the construction of the intermediate school and renovations for the middle school. The new maximum project number is $72 million and the new maximum building cost number is $39.5 million. Inflation in materials caused the bids to exceed an 8% threshold permitted by state law. The district will hold a public hearing on the new numbers on July 27 at 5:00 pm. The meeting will detail the specific factors that led to the cost increase. The public is invited to attend the public hearing and register their opinion with district leaders.
Trinity To Revise Construction Costs For Middle School
July 22, 2022 4:04 am